Cost
How to calculate PCB CAM engineering time and cost
Before deciding whether any panelization tool is worth buying, it helps to know what panelization costs you now. The arithmetic is simple; the care is in the inputs.
1. Measure the time per job
Time a representative set of jobs - say ten - from the moment the prepared data is ready to the moment the panel files are released, including the check. Use the average, and note how much it varies between simple and complex jobs.
2. Count the workload
Count the panelization jobs the whole team does per working day, and the working days per month. This is the team's total; do not multiply it by the number of engineers, or the work is counted twice.
3. Use a fully loaded hourly cost
Salary alone understates the cost of an engineering hour. A fully loaded figure includes benefits, workstation, software and overheads. If you do not have one, use salary per hour and treat the result as a lower bound.
4. Do the arithmetic
- jobs per month = jobs per day × working days;
- hours per month = jobs per month × minutes per job ÷ 60;
- cost per month = hours per month × hourly cost.
Example, purely illustrative: 10 jobs a day for 22 days is 220 jobs. At 25 minutes each that is about 91.7 hours a month; at $15 an hour, about $1,375 of engineering time.
5. Compare a tool honestly
Estimate the new time per job with the check included, repeat the calculation, and take the difference. Then subtract the tool's cost for the same period. Two cautions:
- Time value is not cash. Hours saved are only money saved if they are used for other paid work or avoid overtime or hiring.
- If the new time is longer, it is a loss. Say so rather than hiding it.